News > Load out of Living Quarter topside of SALMAN Oil & Gas field (LQ3)
Sun - 20 Jan 2008

Reference made with MANA Report, LQ3 Topside in Weight of 2000 tons has been loaded Out in Bandar Abbas port.
According to the Same Report, LQ3 Topside Which is Living Quarter of SALMAN oil & gas field Development Project, has been placed on transportation barge and at the present time, it is ready for transportation.
The above mentioned topside has got five floors and the height of its Helideck from the sea level is about 40 meters.
It is expected that after clearing the weather conditions, installation operation of this huge topside will be completed till next 2 weeks.

LQ3 is the biggest topside of SALMAN Oil & Gas Field which will be installed by Lifting method.
Moreover, the load out operation of GLP (last topside of SALMAN field’s which injects gas to the satellite platforms) will be accomplished around one month after LQ3 installation.
After GLP Installation, all marine structures of SALMAN-DALAN Oil & Gas Field will be installed completely and this field would be capable to produce 540 millions cubic foot gas & 50000 barrels of crude oil.



Related Images
Start of SPD 25 & 26 Jackets Legs Construction
Mon - 05 Sep 2011

SPD 25 & 26 Jackets Legs Construction Will Start with  Start of Steel Cutting Operation at 2011/05/09.Jackets of SPD25 & SPD26 are a part of Phases 17&18 South Pars Development Field Which Located Offshore, Some 100 Km South West Of Assaluyeh, in the Persian Gulf, Iran.Platform ...