News > KPP Topside Load out Operation
Wed - 14 Nov 2007
On 14th November 2007, KPP topside in weight of 7500 tons, loaded out in SADRA industrial Island by Iranian elite specialists of  "Deep Offshore Technology" Co. and placed on SADRA FLB124 cargo barge by SKIDDING method. Its sea-fastening operation is also ongoing.
KPP topside with eight legs and dimension of about 50x50x20 m, is the biggest production platform in Persian Gulf from point of dimension and weight.
KPP topside would initially produce gas extracted from DALAN gas field wells. About 550 millions cubic feet of gas per day (CFD) is transferred to Siri Island in Persian Gulf through subsea pipeline.  About 800 barrels of gas condensate are also transferred to existing facilities per day.
Deep Offshore Technology Co., will install KPP Topside, by float over method at offshore site upon completion of sea fastening operation.

 

 

 

 

 

 

 

 

 

 

 

 

 

 



Related Images
Start of SPD 25 & 26 Jackets Legs Construction
Mon - 05 Sep 2011

SPD 25 & 26 Jackets Legs Construction Will Start with  Start of Steel Cutting Operation at 2011/05/09.Jackets of SPD25 & SPD26 are a part of Phases 17&18 South Pars Development Field Which Located Offshore, Some 100 Km South West Of Assaluyeh, in the Persian Gulf, Iran.Platform ...